The Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed developer to give an undertaking that the firm will cover any losses suffered by five home buyers, who got refund orders for delayed possession last month, till the filing of an appeal with the appellate tribunal.
On September 27, 2018, MahaRERA had ordered the developer to refund the investments of five home buyers – Rahul Bhosale, Hitesh Shah, Riyaz Jetham, Alistair Gomes and Sachin Kadam – who had booked flats in Acropolis project in Virar through a subvention scheme in which buyers paid eight per cent of the flat consideration and the banks paid the remaining 92 per cent. The order was to be executed by the developer within 30 days from the date of the order.
The subvention scheme itself is a very big scam, in this scheme the builder gets almost 95% of the loan amount on signing of the agreement without laying a brick, unlike regular home loan where the bank pays to the builder as per progress of the work, the builder lures the home buyers on promise to pay EMI till he hands over the possession, but when builder fails to construct or give possession on time the liabilities comes on the home buyer and the home buyers becomes defaulter and not the builder, in subvention scheme builder charges 10% more then the market value which the buyer realises on the later stage, subvention scheme is design to cheat home buyers.
The developer approached MahaRERA again on October 11 and got a stay on the order till October 24. On October 24, the matter was heard again, and the developer sought extension of stay on the execution of the judgment till the end of 60-day appeal period, citing financial crunch to pay the decretal amount that needs to be paid before the Maharashtra Real Estate Appellate Tribunal.
According to Section 43 of RERA, the appellant has to deposit 50 per cent of the amount with the tribunal before the appeal can be heard.
During the hearing before MahaRERA member Madhav Kulkarni, Sulaiman Bhimani, who appeared for the home buyers, strongly opposed the stay petition arguing that home buyers will suffer monetary losses since they had purchased the flats with bank loans and are paying EMIs. He argued that Rahul Bhosale, who had taken two bank loans, had received a foreclosure letter from the bank stating that if dues are paid before a cut-off date, he will get a concession of Rs seven lakh. He argued that home buyers will suffer immediate losses if the stay is extended.
Kulkarni then directed the developer to file an undertaking to make good any losses suffered by the home buyers till the end of the 60-day appeal period which ends on November 26. The stay was granted after developer complied with the undertaking.
Sulaiman Bhimani Legal Consultant Expert RERA & Co-operative Scty Matters Human and Civil Rights Activist President Citizens Justice Forum 9323642081 Sulaimanbhimani11@gmail.com